Operating a 6-high reversible cold rolling mill requires strict control of rolling parameters, equipment condition and operating safety. In a reversible cold rolling process, steel strip is rolled back and forth between the uncoiler, mill stand and recoiler through multiple passes, with the roll gap reduced between passes to gradually achieve the required final thickness.
This practical guide summarizes key operating procedures, inspection points, maintenance requirements and emergency responses for a single-stand 6-high reversible cold rolling mill.
Main Operating Responsibilities
The main operator is responsible for setting the rolling parameters according to the process sheet, including pass reduction, rolling speed, strip tension, roll bending force and intermediate roll position.
During rolling, the operator should continuously monitor strip thickness, strip shape, rolling force, tension, oil temperature and pressure, as well as the operating condition of the emulsion system. Parameters should be adjusted when necessary to maintain stable rolling and product quality.
Before starting the mill, the operator must confirm that emergency stops, safety doors, light curtains and other safety interlocks are functioning properly. Safety protection devices must never be bypassed or disabled.
The auxiliary operator is responsible for steel coil handling, strip head preparation, threading assistance, scrap removal and housekeeping. During roll changing, lifting and installation work must be carried out under unified direction, with personnel staying away from hazardous areas around the mill stand.
Maintenance personnel are responsible for regular inspection and maintenance of the hydraulic, lubrication, transmission, electrical, thickness measurement and shape measurement systems. When maintenance requires entry into the mill stand, the equipment must be stopped, isolated and locked out according to LOTO procedures.
Pre-Start Safety and Equipment Inspection
Before starting the 6-high reversible cold rolling mill, the following items should be checked one by one.
Working Area and Safety Equipment
- Working passages should be free of oil, water and other obstacles.
- Floor and walkway anti-slip conditions should be satisfactory.
- Trench covers should be complete and securely installed.
- Safety doors, light curtains and emergency stop buttons should be functional.
- Alarm and indicator systems should operate normally.
- Fire-fighting equipment should be available.
Hydraulic, Lubrication and Emulsion Systems
Check the hydraulic oil level, temperature and pressure, and confirm that there is no leakage.
The thin-oil lubrication system should provide the required oil pressure. Cooling water should circulate normally without leakage.
The emulsion system should have sufficient level, suitable temperature and concentration, and adequate pressure and flow. Emulsion nozzles should be free from blockage.
Mill Stand and Rolls
The mill stand should be free of strip remnants, metal pieces and other foreign objects.
Check pipes and connections for looseness or leakage. Guides and water wipers should be in the correct position.
Roll surfaces should be inspected for cracks, damaged areas or serious scratches.
Uncoiler and Recoilers
Check the expansion and contraction functions and chucks of the uncoiler and both recoilers.
The mandrels should be free from serious wear or cracking, and the braking and tension systems should show no abnormal alarms.
Measurement and Control Systems
Confirm that the control panel, thickness gauge and shape meter are operating normally.
The AGC, roll bending and intermediate roll shifting systems should be in the required initial position without abnormal alarms.
All personnel should wear the required personal protective equipment, including safety helmets, cut-resistant gloves and protective, slip-resistant safety shoes. Long hair should be secured, and scarves, bracelets and other easily entangled items are prohibited.
If any required safety or equipment condition is not satisfactory, the mill must not be started.
Start-Up Procedure
Before starting, notify all personnel to leave hazardous areas around the mill stand.
Start the systems in the required sequence:
- Start circulating cooling water.
- Start the emulsion system.
- Start the thin-oil lubrication system.
- Start the hydraulic system and wait until oil temperature and pressure become stable.
- Start the thickness gauge and shape meter and complete their self-checks.
- Close all safety doors and confirm that the safety interlocks are active.
- Select inching mode and test the recoiler and main mill drive at low speed to confirm that there is no abnormal resistance or noise.
- Lift the steel coil onto the uncoiler, align it and expand the mandrel to secure the coil.
- Prepare the strip head, guide the strip through the mill and feed it into the roll gap at low speed.
First-Pass Threading and Rolling
Before the first pass, set the initial roll gap, strip tension, roll bending force and intermediate roll position according to the process requirements.
The first pass should be threaded at low speed, typically 5–15 m/min, until the strip reaches and is engaged by the recoiler on the opposite side.
After establishing tension on both sides, reduce the roll gap to the required rolling condition.
Once strip thickness and shape are stable, gradually increase the rolling speed to the value specified by the process requirements.
Multi-Pass Reversible Cold Rolling
Multi-pass reversible rolling is the core operating procedure of a 6-high reversible cold rolling mill.
As the strip approaches the end of a pass, gradually reduce the rolling speed and rolling force and leave sufficient distance for direction reversal.
After reaching the end of the pass:
- Reduce the mill speed to zero.
- Reset the roll gap according to the next pass.
- Establish tension in the opposite direction.
- Start the mill in the reverse direction.
- Continue rolling according to the parameters specified for the next pass.
Each pass should follow the process sheet. Excessive reduction must not be applied in a single pass.
During rolling, the operator should continuously monitor:
- Strip thickness and thickness deviation
- Strip shape
- Strip tension
- Rolling force
- Mill vibration and abnormal noise
- Hydraulic pressure and temperature
- Lubrication conditions
- Emulsion temperature, concentration and flow
If edge waves, center waves or other strip shape problems occur, the roll bending force and intermediate roll position should be adjusted according to the process requirements. Rolling speed should be reduced when necessary.
The emulsion temperature, concentration and flow should remain stable to provide effective cooling and lubrication.
The mill must not be operated beyond its specified maximum rolling force, speed or tension.
If incoming material has edge cracks, peeling, holes or other serious defects, the mill should be stopped. Defective material should not be forced through the mill, as this may cause strip breakage.
Normal Shutdown
For a production break or coil change, gradually reduce the rolling speed to low speed.
Then:
- Release the rolling force and open the roll gap.
- Release the strip tension and cut the strip.
- Remove the finished coil from the recoiler.
- Keep the emulsion and lubrication systems running for a short period to cool the rolls.
- Record the rolling parameters for the processed coil.
Roll Changing Procedure
Roll changing is a high-risk operation and requires strict safety control.
After the rolling task is completed:
- Completely stop the mill and open the roll gap fully.
- Depressurize the hydraulic system and stop emulsion spraying.
- Remove broken strip, metal pieces and other debris from the mill stand.
- Open the safety door on the operating side and position the roll-changing equipment.
- Inspect lifting tools and wire ropes before use.
- Assign a designated person to direct the lifting operation.
- Remove the work rolls, intermediate rolls and backup rolls in the specified sequence.
- Before installing new rolls, check the roll surfaces for cracks or damage and confirm that the bearings are in good condition.
- Install the backup rolls, intermediate rolls and work rolls in the specified sequence and secure the roll seats.
- Withdraw the roll-changing equipment and close the safety door.
- Perform an unloaded inching test to confirm the operation of the roll bending, intermediate roll shifting and AGC systems.
- Run the rolls at low speed for approximately 30–40 minutes to preheat the roll surfaces before returning to production.
During roll changing and other work inside the mill stand, LOTO procedures must be strictly implemented, and designated personnel should remain outside the equipment for supervision.
Routine Inspection
Regular inspection helps identify abnormal conditions before they affect production or equipment safety.
The recommended inspection frequency is:
- Day shift: once every 2 hours
- Night shift: once every 3 hours
- Shift handover: complete inspection of the mill
The main inspection points include:
- Hydraulic station pressure, oil temperature, oil level and leakage
- Lubrication system pressure, temperature and oil level
- Emulsion pressure, temperature, filter differential pressure and nozzle condition
- Mill stand, rolls and bearing housings for abnormal noise, vibration or temperature rise
- Pipes, connections and hydraulic cylinders for leakage
- Recoiler mandrels, chucks and expansion mechanisms for wear
- Safety doors, light curtains, emergency stops and alarm devices
- Oil or water accumulation on the floor and in trenches
- Condition of anti-slip walkways and working passages
Inspection data should be recorded truthfully. Abnormal conditions should include the observed problem and the corrective action taken, with the issue followed through to closure.
Abnormal Conditions and Emergency Response
Strip Breakage
If strip breakage occurs:
- Immediately press the emergency stop and stop the mill.
- Stop the main drive and release hydraulic pressure.
- Confirm that the strip has completely stopped.
- Remove broken strip pieces from the mill stand.
- Carefully inspect the roll surfaces for impact damage or cracks.
- Check the guides, water wipers and pipes for damage.
- After the fault has been eliminated, perform an unloaded test and then a low-speed trial rolling operation before resuming production.
Never reach into the mill stand to remove broken strip before the equipment has completely stopped.
Serious Strip Deviation or Strip Jam
Immediately reduce the speed, open the roll gap, release the tension and stop the mill.
Inspect the guides and strip alignment system. Do not attempt to correct serious strip deviation by forcing the mill to operate at higher speed.
High-Pressure Hydraulic Oil Leakage
Immediately stop the mill and shut down the hydraulic pump.
Personnel should stay away from the direction of the oil spray to avoid injury from high-pressure hydraulic oil.
The hydraulic system must be depressurized before replacing seals or hydraulic pipes. Never tighten hydraulic connections while the system is under pressure.
Abnormal Noise or Severe Vibration
Immediately reduce the speed and stop the mill.
Do not repeatedly inch the mill to investigate the problem. Maintenance personnel should inspect the bearings, rolls, transmission components and other relevant equipment before restarting.
Fire
If hydraulic oil or emulsion catches fire:
- Stop the mill immediately.
- Isolate the oil source.
- Use a dry-powder fire extinguisher.
- Report the incident to the responsible personnel.
- Do not directly spray water onto electrical or hydraulic equipment.
The general principle for emergency response is:
Stop the mill and protect personnel → isolate the energy source → identify and eliminate the fault → confirm safe conditions → record and report the incident.
Maintenance and Repair Safety
Maintenance work on the mill should follow defined isolation and safety procedures.
For work inside the mill stand or on the hydraulic system, the equipment must be stopped, isolated, depressurized and locked out according to LOTO requirements.
For work involving trenches or underground hydraulic areas, applicable confined-space procedures should be followed, including gas testing and external supervision.
After maintenance is completed, the equipment should undergo an unloaded inching test and safety interlock test. Production should only resume after the equipment is confirmed to be operating normally.
Cleaning, tightening or other work on rotating components while the equipment is running is strictly prohibited.
Key Safety Rules
The following safety requirements should be treated as non-negotiable:
- Never bypass or short-circuit safety doors, light curtains or emergency stops.
- Never put hands or tools into the mill stand or pinch-point areas while the equipment is running.
- Never exceed the specified rolling force, tension or design speed.
- Never tighten hydraulic connections while they are under pressure.
- Never stand or walk beneath suspended rolls or steel coils.
- Never enter the mill stand before the equipment has completely stopped.
- Never force-roll material with serious defects.
- Never operate the mill when fatigued, under the influence of alcohol or otherwise unfit for work.
Preventive Maintenance
Routine maintenance should be carried out according to the equipment maintenance schedule.
Daily maintenance includes cleaning metal debris and oil from the mill stand, checking for leakage and testing emergency stop functions.
Weekly maintenance includes cleaning the emulsion filters, clearing blocked nozzles and checking pipe connections and fasteners.
Monthly maintenance includes hydraulic and lubrication oil sampling, hydraulic cylinder seal inspection and instrumentation calibration.
Annual maintenance includes comprehensive equipment inspection, inspection of the mill housing and transmission system, pipe thickness measurement and dedicated safety system testing.
Maintenance activities should be recorded in equipment maintenance logs to ensure traceability.